Ardrossan Project Update (January 2026)

Progress in this period includes:

  • continued operation under the Safe System of Works
  • removal of contaminated stockpiles from the southern part of the site
  • continuation of foul drainage installation
  • continued surface water drainage installation
  • continuation of swimming pool excavation and preparing piles for next stage of construction
  • commencement of foundations in teaching wing

Works to be undertaken in the next four weeks include:

  • continuation of foul drainage installation
  • continued surface water drainage installation
  • continuation of swimming pool excavation and preparing piles for next stage of construction