Ardrossan Project Update (January 2026)
Progress in this period includes:
- continued operation under the Safe System of Works
- removal of contaminated stockpiles from the southern part of the site
- continuation of foul drainage installation
- continued surface water drainage installation
- continuation of swimming pool excavation and preparing piles for next stage of construction
- commencement of foundations in teaching wing
Works to be undertaken in the next four weeks include:
- continuation of foul drainage installation
- continued surface water drainage installation
- continuation of swimming pool excavation and preparing piles for next stage of construction