Ardrossan Project Update (August 2025)

News |

Ardrossan Project Update (August 2025)

Progress in August includes:

  • Site set up and enabling works
  • Site surveys and testing
  • Dilapidation surveys
  • Installation of noise, vibration and dust monitors at points in site closest to neighbouring properties.
  • Site security installation of heras fencing and CCTV
  • Preparation of piling platforms and piling commencement

Works to be undertaken in September include:

  • Continuation of site set up including installation of remaining hoarding and installation of additional site welfare
  • Continuation of surveys
  • Continuation of piling. We are really excited to be the first project in the UK to use a fully electric piling rig – more to come on this soon! Please be aware that whilst we aim to keep disruption to a minimum piling work will create noise and possible vibration
  • Sheet Piling for swimming pool excavations
  • Commence drainage installation
  • Cutting down piles to platform height