    Ardrossan Project Update (August 2025)
Progress in August includes:
- Site set up and enabling works
- Site surveys and testing
- Dilapidation surveys
- Installation of noise, vibration and dust monitors at points in site closest to neighbouring properties.
- Site security installation of heras fencing and CCTV
- Preparation of piling platforms and piling commencement
Works to be undertaken in September include:
- Continuation of site set up including installation of remaining hoarding and installation of additional site welfare
- Continuation of surveys
- Continuation of piling. We are really excited to be the first project in the UK to use a fully electric piling rig – more to come on this soon! Please be aware that whilst we aim to keep disruption to a minimum piling work will create noise and possible vibration
- Sheet Piling for swimming pool excavations
- Commence drainage installation
- Cutting down piles to platform height
 
    
 
    
 
    