    Ardrossan Project Update (September 2025)
Progress in September includes:
- Site set up and enabling works
- Site surveys and testing
- Site security installation of heras fencing, hoarding and CCTV
- Completion of piling works
- Continued drainage works
- Continued cutting of piles to platform height
Works to be undertaken in October include:
- Continuation of site set up including installation additional site welfare.
- Continuation of surveys
- Continuation of drainage
- Commencement of foundations and concrete slab preparations
- Commencement of steel frame erection
 
    
 
    
 
    