Ardrossan Project Update (September 2025)

News |

Ardrossan Project Update (September 2025)

Progress in September includes:

  • Site set up and enabling works
  • Site surveys and testing
  • Site security installation of heras fencing, hoarding and CCTV
  • Completion of piling works
  • Continued drainage works
  • Continued cutting of piles to platform height

Works to be undertaken in October include:

  • Continuation of site set up including installation additional site welfare.
  • Continuation of surveys
  • Continuation of drainage
  • Commencement of foundations and concrete slab preparations
  • Commencement of steel frame erection