Ardrossan Project Update (April 2026)
Progress in the period includes:
- Continued operation under the Safe System of Works
- Continuation of foul drainage installation
- Continued surface water drainage installation
- Completion of service track installation
- Recommence foundations in Central Wing
Works to be undertaken in next four weeks include:
- Continued operation under the Safe System of Works
- Continuation of foul drainage installation
- Continued surface water drainage installation
- Continued foundations in Central Wing
- Commence steel frame deliveries
- Commence steel erection