Ardrossan Project Update (April 2026)

News |

Ardrossan Project Update (April 2026)

Progress in the period includes:

  • Continued operation under the Safe System of Works
  • Continuation of foul drainage installation
  • Continued surface water drainage installation
  • Completion of service track installation
  • Recommence foundations in Central Wing

Works to be undertaken in next four weeks include:

  • Continued operation under the Safe System of Works
  • Continuation of foul drainage installation
  • Continued surface water drainage installation
  • Continued foundations in Central Wing
  • Commence steel frame deliveries
  • Commence steel erection