Ardrossan Project Update (February 2026)
Progress in the period includes:
- Continued operation under the Safe System of Works
- Continuation of foul drainage installation
- Continued surface water drainage installation
- Completed swimming pool excavation and trimming piles
Works to be undertaken in next four weeks include:
- Continuation of foul drainage installation
- Continued surface water drainage installation