Ardrossan Project Update (July 2026)
What’s been happening?
Over the last four weeks, we’ve made good progress across the site:
- Completion of the foundations and walls for the swimming pool plant room and balance tank.
- Continued foundation works within the gym hall area.
- Ongoing formation of the new car park.
- Continued construction of the swimming pool floor.
- Progress on the steel structure erection for the Central Wing.
- Continued installation of scaffolding, access platforms, and safety handrails.
- Commencement of concrete floor slab works within the Teaching Wing.
- Commencement of sports pitch formation works.
What’s coming next over the next 4 weeks?
- Continuing foundation works within the Sports Wing.
- Continuing scaffolding, access, and handrail installations.
- Continuing the installation of concrete staircases.
- Continuing concrete floor slab works within the Teaching Wing.
- Continuing formation of the sports pitches and car park areas.
- Beginning installation of metal decking within the Central Wing.
- Beginning construction of floor slabs within the Central Wing.
- Beginning installation of external wall framing to the Teaching Wing.
- Beginning roofing works to the Teaching Wing.