News
|
Ardrossan Project Update (May 2026)
Progress in the period includes:
- Completion of operations under the Safe System of Works.
- Completion of foul drainage installation.
- Completion surface water drainage installation.
- Continued foundations in Central Wing.
- Commenced foundations in the gym hall.
- Commenced pool plantroom & balance tank foundations and walls.
- Commenced steel erection to Teaching Wing.
- Commenced formation of soft landscaping mounds.
Works to be undertaken in next four weeks include:
- Completed foundations in Central Wing.
- Continue steel frame erection in Teaching Wing.
- Continue foundations in Sports Wing.
- Continue pool balance tanks & plantroom walls.
- Commence scaffolding access and handrails.
- Commence concrete stairs installation.
- Commence metal decking to Teaching Wing.