SOSC October 2026 Progress

Latest Drone Footage and Update - October 2026

News |

Project Update - October 2026

Morgan Sindall Construction zones progress during October 2026 as follows:

Community Hub

The community hub internal finishes are nearing completion with ceilings closed and services works to the commercial kitchen and multi-use spaces. Flooring ongoing and will be completed next month. Testing and commissioning has started following connection to the new substation. Covered court base has been installed along with lighting and floor sockets for netball and tennis. Finished decorations are well underway and permanent lighting started.

Alpine Snow Sports Centre

Works completed ready for BH Live storage fit out.

Athletics Pavilion and Grandstand

Pavilion complete and BH Live have moved into this building with operational use.

Woodland Car Park

Works completed and handed over to SCC.

Family Zone

Works completed ready for handover to SCC.