Mallory & Irvine, Wirral

Two new build, five storey office blocks in the heart of Birkenhead, with low carbon and waste objectives. Delivered as part of the Birkenhead 2040 framework, the project is part of a masterplan to regenerate and transform the town.

Key Stats

  • 150,000 sq ft offices
  • Shell & Core
  • CAT A/CAT B fit out
  • Two five storey buildings
  • Steel frame
  • Two Stage Design & Build
  • BREEAM Excellent
  • Wired Score Gold
  • WELL Standard enabled
  • Over 800t carbon savings through design
  • WINNER: Value Award and Contractor of the Year - Constructing Excellence NW Construction Awards 2024
  • WINNER: Considerate Constructors Scheme National Site Awards - SILVER

At a Glance

Client

Wirral Growth Company

Budget

£39.8m

Completion

September 2023

Location

Birkenhead

Sector

Commercial

Social value

£22m Verified Social Value

Sustainability

800 tonne Embodied Carbon Saving

BACKGROUND TO MALLORY & IRVINE

Forming part of the Birkenhead 2040 framework, Mallory & Irvine marked a significant milestone in the regeneration of Birkenhead and the creation of a new business and leisure quarter in the heart of the town.

Led by Wirral Growth Company, a joint venture between Wirral Council and Muse Developments, the scheme delivered 150,000 sq ft of Grade A office accommodation across two five-storey buildings.

The BREEAM Excellent development combined high-quality modern workspace with distinctive architecture, strong sustainability credentials and a commitment to creating lasting social and economic benefits for the local community.

SUSTAINABLE AND INNOVATIVE DESIGN

The two buildings feature contrasting façades, with one finished in traditional brickwork and the other incorporating a distinctive bespoke terracotta cladding system.

As a novel façade solution, the terracotta system was carefully developed, tested and refined with the specialist supply chain to ensure buildability, quality and efficient installation. Early design development and collaboration across the wider project also helped improve buildability, programme certainty and overall project efficiency.

Mallory & Irvine was an early adopter of Morgan Sindall’s CarboniCa carbon calculation model, enabling carbon to be considered alongside cost, programme and buildability as the design developed.

CarboniCa was used to identify and assess opportunities for reducing embodied carbon, helping the project team make informed, lower-carbon choices throughout design and procurement. This approach contributed to significant savings against the project’s original carbon baseline and supported the delivery of two BREEAM Excellent buildings.

INVESTING IN THE FUTURE OF BIRKENHEAD

The project provided an important opportunity to ensure investment in the town created benefits beyond the buildings themselves.

Working closely with Wirral Council and Muse Developments, we developed a social value strategy around identified local priorities and the particular socio-economic challenges facing communities across the Wirral. This allowed activity to be targeted where it could have the greatest impact, with three principal areas of focus:

  • Creating Wirral’s future workforce
  • Supporting care leavers
  • Generating sustainable business growth

A key part of this was our educational partnership with Wirral Met College, helping ensure local students could benefit directly from a major construction project taking place in their community. We co-branded our onsite Knowledge Quad training and learning facility with the college, creating a dedicated environment where students could engage with the project and learn directly from our teams and specialist supply chain.

Wirral Met College Students visit our Wirral Knowledge Quad to Explore Apprenticeship routes into construction

Through site visits, practical learning and training opportunities, students gained first-hand insight into live construction, the range of careers available within the industry and the skills required to progress into employment.

Alongside this, we supported disadvantaged groups into work and helped local SMEs and suppliers access opportunities generated by the development, ensuring the project contributed to wider skills development, employment and sustainable economic growth across the Wirral.

Key outcomes

  • £22m Social Value (55% SVA) Verified by Social Value Portal
  • Wirral College partnership: meaningful engagement for 568 students
  • Over 1000 Apprentice/work experience wks
  • 84 people from disadvantaged groups into work, including 10 new jobs for care leavers
  • 13 Community projects including £57,204 materials donations and 1,055 volunteering hours

Your approach to partnership working and the genuine difference you have made to some of our most disadvantaged residents should be held up as best practice, including your ground-breaking education partnership with Wirral Met College and the on-site Knowledge Quad.” Beverley Staniford, Economic Development Manager