Stevenage Leisure view from behind the hoardings

Stevenage Leisure Centre - May newsletter

News

We have now commenced initial enabling works on site and the hoarding installation to site boundary is now complete and site secured. Additionally, a new vehicle access to the site has been constructed off Fairlands Way and the existing vehicle access off St. Georges Way is now closed.

Works to construct a new pedestrian crossing across St. Georges Way will also be progressed.

We will be progressing with the following works over the next period:

  • Drainage works to both car park areas
  • Demolition of the single-storey extension of the existing Swimming Centre
  • Construction of piling matt in readiness for the main construction works.

If you have any further queries please contact Maurice Wilson, Project Manager on

[email protected]